A Spring Solar Build Starts in Winter: Do the Geotechnical Work While the Ground Is Frozen

Geotechnical EngineeringRenewable EnergyTechnical Insights

Foundation design for a solar or wind project depends on site investigation and pile load testing, and both take time to review. Doing the investigation and preparation over the winter lets testing start at the thaw and design follow without a gap.

A solar project that waits for spring to start its geotechnical program loses the first weeks of the building season to drilling, lab work and review. A project that started in January can be load testing piles as soon as the frost leaves the ground, and ordering production piles soon after.

On most ground-mounted solar sites in Canada, racking sits on driven steel piles. Their design is governed by uplift and lateral loads from wind, by the soil they are driven into, and by frost. Each of those has to be understood before pile lengths and sections are fixed, and some of it can only be confirmed by testing piles on site.

Much of that work does not need thawed ground. A desktop review of surficial geology, water well records, topography and any earlier reports on or near the site can start at any time and shapes everything that follows. Drilling can often go ahead in winter, and on wet or soft sites frozen ground can make access easier than it will be in spring. Lab testing on recovered samples, including moisture content, gradation and the soil chemistry that affects corrosion of steel piles, runs indoors at a PRI CCIL-Certified Laboratory. Preliminary foundation design and the layout of test piles across the different ground conditions on site can be settled before the thaw.

Pile load testing is the part that has to wait, and the timing matters. Frozen soil is stronger than the same soil thawed, so a test on a pile embedded in frozen ground can overstate the capacity it will have in summer. Tests should be scheduled once the frost has left the depth that matters, or the results interpreted for the frost conditions present when the test was run. Frost also works the other way. As the ground freezes, it can grip a pile and push it upward, and that uplift has to be part of the design.

Spring access is the other constraint. Thawing sites are often soft, and heavy equipment can damage the ground or get stuck. A test program planned in winter, with test locations, access routes and equipment chosen in advance, can start as soon as the site can take it.

The objection is cost. Winter drilling can cost more, and an owner may not want to spend on investigation before every approval or contract is in place. Against that sits the cost of a late start: a short building season, crews and equipment booked for dates the design is not ready for, and production piles ordered before their lengths are confirmed.

The timing matters beyond the site, too. Budget 2026 extends the Clean Technology and Clean Electricity investment tax credits to the end of 2040, and widens the electricity credit to cover the highest-voltage transmission lines in each province. Writing on the budget this month, Jesse Unke, Vice President, Transportation and Infrastructure at PRI, made the point that faster approvals and new funding will need to be matched by stronger project development, engineering and construction capacity. On a solar or wind build, much of that capacity is set by the work done before the season opens.

Building Canada’s clean energy future together depends on projects that start on time. On a project that builds in the thaw, the work done in winter decides how soon the first pile goes in.

Planning a solar or wind build for spring? We would be glad to help you use the winter well. Let’s start the conversation.